2021–2023 · Design & build

Yagna Pavilion

A permanent place for havan, Agnihotra, and gathering together.

It started in 2021 as a fire altar on an open platform. By 2023 it was a roofed pavilion. My father and I built it in stages, and each version showed us what the next one needed.

Follow the build ↓
The completed pavilion in winter, with its raised central roof visible above the main roof.
The finished pavilion, in winter
My role
Designed and built it with my father
Footprint
Approximately 35 × 30 ft
1,050 sq ft
Project cost
Approx. total project cost: $22,000

Why I built it

We do havan and Agnihotra at home, and I wanted the havan kund to have a permanent place: somewhere we could keep coming back to, together. Everything else followed from that. The layout, the altar at the center, and eventually the roof.

From ground to gathering place

The completed pavilion in winter, with its raised central roof visible above the main roof.
01 / 08
Still standing, in snow

The finished pavilion in winter. The raised cap over the center lets smoke out and keeps rain off.

Compacted aggregate, a plate compactor, and staged pavers before the first surface was laid.
02 / 08
Getting the ground ready

Summer 2021. Compacted gravel, a rented plate compactor, and the pavers stacked and waiting.

Placing and aligning the outdoor pavers by hand.
03 / 08
Laying the first floor

Pavers set by hand, one at a time, with spacers to keep the gaps even.

Rain across the first paver field during construction, with unfinished areas and altar forms visible.
04 / 08
Then it rained

June 2021. A storm hit before we had finished, and water sat right across the platform.

Timber forms and cut pieces around the central work area.
05 / 08
Forms for the altar

Timber forms for the stepped base of the altar, poured in stages.

The finished stepped altar and the surrounding paver platform arranged for a gathering.
06 / 08
Version one, done

September 2021. An open paver platform around the stepped altar.

White stepped finishes, lamps, and seating around the central fire cavity.
07 / 08
The havan kund in use

November 2021. Lamps, seating and the fire, the reason the whole thing exists.

A wider view of the completed roofed structure and its setting.
08 / 08
Version two

February 2023. Eight posts, a hipped roof, and a raised cap over the fire.

01 / Clearing and layout

Start with the ground.

My father and I cleared the ground, staked out the rectangle with string, and checked it with a level. We stripped the topsoil and weeds and put down landscape fabric before anything else.

Most of the work that decides whether a floor stays flat ends up buried under it, where nobody sees it again.

Compacted aggregate, a plate compactor, and staged pavers before the first surface was laid.
Compacted aggregate, a plate compactor, and staged pavers before the first surface was laid.

02 / Gravel, sand, pavers

A floor laid by hand.

We spread crushed stone, compacted it with a rented plate compactor, and topped it with a thin layer of sand. The pavers sit on that sand, so any low spot underneath shows up on the surface. I ran string lines and checked with a level the whole way across.

I laid the pavers with spacers to keep the gaps even, and cut pieces to fit around the edges and the altar. The pattern gives the gathering area a clear edge around the fire.

Placing and aligning the outdoor pavers by hand.
Placing and aligning the outdoor pavers by hand.

03 / The custom altar

The center came first.

The whole platform exists for the havan kund, so I designed that first. The fire sits in an upside-down truncated pyramid: a small square at the bottom that opens wider toward the top. I built a removable form for it, poured the stepped base around it in stages, and cut the white finish pieces for the steps and edges.

I also had to think about where people sit. Everyone gathers around the fire, not just in front of it, so the platform grew out from the altar instead of the altar being dropped onto a platform.

White stepped finishes, lamps, and seating around the central fire cavity.
White stepped finishes, lamps, and seating around the central fire cavity.

04 / Weather and the rebuild

Then it rained.

In June 2021, before we had even finished, a storm left water standing across the platform. Once the first version was done that September, we used it, and the weather kept deciding when we could. An open platform only works on good days.

So the second version had two jobs: shelter, and a better floor. We pulled up the pavers but kept the compacted base under them. I set the perimeter forms and helped pour one continuous concrete platform, and we rebuilt the altar too.

Rain across the first paver field during construction, with unfinished areas and altar forms visible.
Rain across the first paver field during construction, with unfinished areas and altar forms visible.

05 / Timber frame and roof

A roof with a hole in it.

We laid out eight post locations, set the timber posts, braced them, and checked plumb, level and the diagonals before anything went on top. Beams around the perimeter and sloped roof members tie it all together around a 5 × 4 ft opening in the middle.

That opening is there on purpose. A fire under a solid roof leaves the smoke nowhere to go, and hot air rises, so the natural exit is straight up over the fire. I kept the opening and built a small raised roof above it: smoke leaves through the sides of the cap, and rain can’t fall straight in. I haven’t measured how well it actually clears smoke.

Then sheathing, underlayment, shingles, flashing and trim, and everything primed and painted white. It was finished by February 2023.

A wider view of the completed roofed structure and its setting.
A wider view of the completed roofed structure and its setting.

06 / Finish and continuing improvements

Still not finished.

I laid the final outdoor tile over the new slab, set out the pattern and cut the edges. That pulled the altar, the seating and the shelter into one place.

The sides are still open, so wind-driven rain still gets in. Next I’m looking at removable screens, a few polycarbonate panels, and better control of where the runoff goes. Those are ideas, not done yet.

Interactive structural model

How the pavilion stands.

How it’s put together: the slab and footings, eight posts, the perimeter beams and roof framing, and the raised cap. Pull the layers apart, or follow the weight of the roof down to the ground.

Model of the pavilion: eight white columns around the central havan kund under a dark hipped roof with a raised vent cap.

The pavilion as built: eight columns around the havan kund under a hipped roof with a raised vent cap.

Drag sideways to rotate. In Structure and Exploded, select a part to see the construction photograph behind it.

Working at this scale

Footprint and perimeter.

Simple numbers, but every material estimate starts here.

Footprint calculations
ItemCalculationResult
Footprint35 ft × 30 ft1,050 sq ft
Perimeter2 × (35 + 30) ft130 ft

Geometry and the next drawing

Working through the numbers.

What I know for sure: the 35 × 30 ft platform, the 10 ft eave height, and the 5 × 4 ft opening. Everything else comes from those.

01 / Roof form

A hipped main roof rises from the eaves, about 10 ft above the floor, to the edge of the 5 × 4 ft central opening. A smaller raised roof covers the opening, its 5 ft side parallel to the 35 ft side of the platform.

02 / Why rain still reaches the platform

The sides are open, so wind-driven rain still reaches the floor. The next version has to deal with screens, splash, and where the water goes once it leaves the eaves.

03 / Central opening and passive ventilation

Aopening = 5 × 4 = 20 ft² = 2,880 in²

The opening is about 1.9% of the platform area. I wanted hot air and smoke to have a way straight out, with a small roof above to keep the rain off.

How much actually flows depends on the gap under the cap and the framing around it, so the area alone doesn’t tell you the airflow.

04 / Following the load path

Roof covering → sheathing → rafters and hip members → beams → eight posts → footings → ground

See this path in the model ↑

I use this chain to decide what a measured drawing needs: member sizes and spans, where the loads enter the beams, the connections, and the footings. Photos can show the path, but not how much each piece can carry.

05 / What the measured drawing will add

Next, I’m turning my hand sketch into a measured drawing: floor and roof outlines, post locations, the real runs and rise, the cap, member sizes, connections and drainage. With those I can work out the roof area, the loads and a proper cut list.

I also want the next materials count to separate what got installed from what got cut off or reused. The table below is what both versions actually cost.

Across both major build phases

Approx. total project cost: $22,000.

From my cost sheet, across both versions: materials, equipment rental, delivery and consumables for the first platform and the rebuild. Our own labor isn’t counted.

Approximate spending by phase · expand a phase for materials
Build phase and materialsApprox. cost
Site clearing and layout

Stakes, string and marking supplies; clearing consumables; landscape fabric and staples.

$400
Compacted aggregate and sand base

Crushed aggregate, bedding sand, border materials, and plate-compactor rental.

$1,400
Original paver platform

Outdoor pavers, joint sand, spacers, masonry cutting consumables, and delivery.

$3,300
Original havan kund

Custom form material, staged concrete/cement pours, white finish pieces, mortar, grout, and tile-cutting tools.

$1,100
Concrete/cementitious rebuild

Perimeter forms and bracing, platform material, leveling and finishing tools, and removal/cleanup consumables.

$3,000
Eight column footings

Footing concrete, setup materials, temporary bracing, and post-setting hardware.

$500
Timber frame

Eight main columns, perimeter beams, sloping roof members, blocking, central-opening framing, and temporary braces.

$2,500
Roof and passive vent

Sheathing, underlayment, shingles, flashing, edge details, fastening hardware, and trim for the raised roof.

$3,200
Paint and exterior finish

Exterior primer and white paint, caulk/sealant, brushes, rollers, and preparation supplies.

$550
Final exterior floor tile

Outdoor stone-look finish, exterior mortar, joint material, sealer, and cutting tools.

$3,500
Other equipment, delivery and consumables

Mixing and finishing equipment, cutting/fastening tools, hauling, hand tools, protective equipment, miscellaneous supplies, and waste allowance.

$2,550
Approximate total$22,000

What I learned

A finished version isn’t the final version.

Every fix showed us the next problem. A good floor didn’t help when it rained. A roof helped, but the open sides still let rain in. Now I start by asking how a space will actually be used, not just how it should look.

Building it with my father also showed me how much of building is checking: align, brace, measure, adjust, and only then move on. It matters to me because we built it together, and because people actually gather there.